Air Bricks in house


Postby fcwoods99 » Sat May 09, 2009 6:27 pm

I know over the years ground level has been lifted on my house and needs lowering !
At the moment my ground level around the back of the house is 3inch above air bricks !
How far below air brick should ground level be ?
Last edited by fcwoods99 on Wed May 13, 2009 10:50 am, edited 1 time in total.
fcwoods99
Posts: 15
Joined: Wed Nov 28, 2007 12:23 am

Sponsor

Simply Build It

Postby stoneyboy » Tue May 12, 2009 8:41 pm

fcwoods99,
The ground level should be at least 2 courses below the DPC level, If the air bricks were installed correctly they should then be above ground level.
end
stoneyboy
Posts: 2708
Joined: Wed Dec 10, 2008 6:44 pm


Postby rosebery » Wed May 13, 2009 10:26 pm

I've just given fundamentally the same answer in your other thread without realising you had created two. One thread is normally enough for each problem.

Cheers
rosebery
Posts: 2022
Joined: Wed Sep 26, 2007 8:55 pm


Postby fcwoods99 » Thu May 14, 2009 9:03 pm

glad you noticed
cheers for help :D
fcwoods99
Posts: 15
Joined: Wed Nov 28, 2007 12:23 am