Bathroom Pipework Issues During Modifying Bathroom


Postby Rockabilly » Mon Aug 22, 2016 10:20 am

Hi, I am currently modifying our bathroom.
I have removed the shower unit and sink and I'm replacing with bath and new sink.
My problem is the pipework!
I have a 15 mm feed off the mains that fed to feed the shower which I've capped off.
I have a 15mm hot feed from boiler for the sink and a 15mm cold from a tank in loft that is cold supply for sink and toilet.
Now can I use the mains supply to feed sink, toilet and bath?
Therefore get rid of tank in loft?
Can I tee off the hot supply to feed bath?

Any advice very much appreciated.
Cheers Craig
Rockabilly
Rank: Labourer
Progress to next rank:
50%
Posts: 3
Joined: Mon Aug 22, 2016 10:01 am

Sponsor

Simply Build It

Postby lets have a look » Mon Aug 22, 2016 5:33 pm

Depends if you have a combi boiler
lets have a look
Rank: Foreman
Progress to next rank:
4.3%
Posts: 213
Joined: Sun Mar 20, 2016 7:59 am

Postby Rockabilly » Mon Aug 22, 2016 11:21 pm

Sorry yes combie boiler
Rockabilly
Rank: Labourer
Progress to next rank:
50%
Posts: 3
Joined: Mon Aug 22, 2016 10:01 am

Postby lets have a look » Tue Aug 23, 2016 5:17 pm

Yes you can connect the bathroom to the cold mains and tee off the 15mm hot pipe for the bath
lets have a look
Rank: Foreman
Progress to next rank:
4.3%
Posts: 213
Joined: Sun Mar 20, 2016 7:59 am

Postby Rockabilly » Tue Aug 23, 2016 6:04 pm

Great... Thank you
Rockabilly
Rank: Labourer
Progress to next rank:
50%
Posts: 3
Joined: Mon Aug 22, 2016 10:01 am

Display posts from previous
Sort by
Order by



  • DIY How to Project Guides

  • DIY how to tutorial projects and guides - Did you know we have a DIY Projects section? Well, if no, then we certainly do! Within this area of our site have literally hundreds of how-to guides and tutorials that cover a huge range of home improvement tasks. Each page also comes with pictures and a video to make completing those jobs even easier!



 


  • Related Topics