How long before I can mist coat?

Postby scroogemonster » Wed Apr 27, 2011 7:13 pm

Hi all, I have had a lounge room taken back to the brick and replastered. Two coats of sand and cement on walls followd by skim coat. All walls appear dry (light pink colour) and the ceiling (was boarded over and skimmed) has been mist coated already.
How long should I leave it before mist coating the walls. It has been 4 weeks exactly since plastering has ended.
Rank: Apprentice
Progress to next rank:
Posts: 23
Joined: Thu Aug 16, 2007 3:41 pm


Simply Build It

Postby theshedman » Thu Apr 28, 2011 7:57 am

Hi, it should be fine to mist coat if it is a light pink colour as this will mean that it has dried out.
Rank: Foreman
Progress to next rank:
Posts: 210
Joined: Thu Jul 09, 2009 11:11 am

Postby chris_on_tour2002 » Sun May 08, 2011 9:51 am

four weeks is plenty of time.

the textbook will tell you to wait 4-6 weeks but in reality most people will mist coat as soon as the plaster has dried out, when it turns from the dark brown to light pink colour.
Rank: Project Manager
Posts: 1023
Joined: Thu Aug 30, 2007 9:14 pm

Display posts from previous
Sort by
Order by

  • DIY How to Project Guides

  • DIY how to tutorial projects and guides - Did you know we have a DIY Projects section? Well, if no, then we certainly do! Within this area of our site have literally hundreds of how-to guides and tutorials that cover a huge range of home improvement tasks. Each page also comes with pictures and a video to make completing those jobs even easier!


  • Related Topics