Plasterer or carpenter first?

Post by pickup01 » Tue Mar 13, 2007 11:38 am

I have a room which needs the old wood work (skirting boards/architraves&doors) replaced and comletely replastering. What's the order of work for this?

thedoctor
Posts: 2530
Joined: Sat Apr 08, 2006 12:15 pm

Post by thedoctor » Fri Mar 16, 2007 1:39 pm

MANY OF THE ANSWERS TO YOUR POSTS CAN BE FOUND, WITH DIAGRAMS, IN THE DIYDOCTOR PROJECTS SECTION. CLICK HERE www.diydoctor.org.uk/projects.htm

omulcol
Apprentice
Apprentice
Posts: 6
Joined: Wed Mar 28, 2007 6:36 pm

Post by omulcol » Wed Mar 28, 2007 8:22 pm

Take off all the old woodwork - call in the plasterer - then call the carpenter !