Precast concrete steps
All manner of questions and solutions to problems and issues surrounding the subject of brickwork, blockwork and stonework

2 posts   •   Page 1 of 1
Elias
Labourer
Labourer
Posts: 2
Joined: Mon Jun 15, 2009 9:56 pm

Precast concrete steps

Post by Elias » Mon Jun 15, 2009 10:10 pm

Hi everyone,i have got a job to do wherby i have to build a raised patio.It is 800mm high from ground level,and on the drawing i have there are 4 200mm(rise) steps leading up to it.The supplier i was going to go to informed me the only steps they now stock have a 175mm rise.Obviously 4 of these steps only total 700mm and 5 of them will amount to 875mm.Does anyone know if there's still a way to use the 175mm steps anyway or will i have to source 200mm steps.Thanks a lot,Elias.

monty_trace
Apprentice
Apprentice
Posts: 6
Joined: Sat Aug 29, 2009 9:52 pm

Post by monty_trace » Sat Aug 29, 2009 10:32 pm

hi, drop your first step 75mm by taking off 1 course of brick under your first step .[/img]

2 posts   •   Page 1 of 1
It is currently Fri Apr 12, 2024 6:46 am