Hi could anyone please confirm the correct supplementary bonding...
All pipework (bath, shower, sink, toilet, radiators) copper within the bathroom but changes to all plastic beneath the floorboards.
Electrics within the room are:
* Pull dimmer switch to downlights [located in unzoned area]
* Shaver socket (off light circuit) [located in zone 3]
* Bathroom mirror light (off light circuit) [located in zone 3]
* Pull light switch to shower cubicle [located in zone 3]
I don't think any supplementary bonding is required - but please correct me!
[quote="DT"]Hi could anyone please confirm the correct supplementary bonding...
All pipework (bath, shower, sink, toilet, radiators) copper within the bathroom but changes to all plastic beneath the floorboards.
Electrics within the room are:
* Pull dimmer switch to downlights [located in unzoned area]
* Shaver socket (off light circuit) [located in zone 3]
* Bathroom mirror light (off light circuit) [located in zone 3]
* Pull light switch to shower cubicle [located in zone 3]
I don't think any supplementary bonding is required - but please correct me!
Any help appreciated.[/quote]
DT
4 mm2 earthing conductor between shower pullcord switch and lightswitch only required.
BLAKEY1963
DIY how to tutorial projects and guides - Did you know we have a DIY Projects section? Well, if no, then we certainly do! Within this area of our site have literally hundreds of how-to guides and tutorials that cover a huge range of home improvement tasks. Each page also comes with pictures and a video to make completing those jobs even easier!