EAL Certified Domestic Installer Course
Ask questions and find answers to many subjects relating to electrics and electrical work

4 posts   •   Page 1 of 1
val101
Apprentice
Apprentice
Posts: 5
Joined: Tue Apr 01, 2008 6:15 pm

EAL Certified Domestic Installer Course

by val101 » Sat May 30, 2009 2:49 pm

hi all

im currently doing the above course and im struggling with a few questions. im fine with the electrical questions, since im studying to be a spark, but on the course you get asked questions which i have no idea about, here is one example -

- Give TWO reasons why it is necessary for the main contractor to produce a schedule of work for an extension

now im not a main contractor, once qualified i would be working for a main contractor as a sub contractor, so i have no idea how to answer this question, could anyone help please

stoneyboy
Project Manager
Project Manager
Posts: 6429
Joined: Wed Dec 10, 2008 6:44 pm

by stoneyboy » Sat May 30, 2009 10:34 pm

val101,
1. So that sub contractors know what to do.
2. So that the work is carried out to a specified standard.
end

kbrownie
Project Manager
Project Manager
Posts: 1995
Joined: Mon Mar 05, 2007 9:36 pm

by kbrownie » Sun May 31, 2009 12:27 am

Well a main contractor duties a varried,
but the upshot is that he needs to manage the build so all other contractors are working in a system that ensures the work is completed on time and other contractor and subbies are there when they should be as are materials required to complete the work ordered.
Hopefully the work is completed on time and on budget.
He may have time restriction during the day, when only certain trades or certain equpment can be used or deliveries can be taken due to enviromental issue regarding noise and traffic restrictions. They may not be allowed to work on weekends or only work on evenings, to name a few.
So needs a plan of action.
KB

rosebery
Project Manager
Project Manager
Posts: 2021
Joined: Wed Sep 26, 2007 9:55 pm

by rosebery » Sun May 31, 2009 8:15 am

You are focussing on the "main contractor" part of the question rather than the real question which is related to work planning.

Think of it this way:

"- Give TWO reasons why it is necessary for the electrical sub-contractor to produce a schedule of work for an extension"

but think of half a dozen reasons and from that you'll have suufficient data to answer the question thats been asked.

Cheers

4 posts   •   Page 1 of 1
It is currently Wed Apr 17, 2024 5:29 pm