I'm new to the forum so I don't know if this is the right forum to post in but I wonder if anyone could help me with timescales for renovating our bathroom. My husband is in a wheelchair and we have a wetroom but it is horrible having been done by the council many moons ago. I would love to install a trendy tiled wetroom without altering the plumbing.
Any ideas on how long this might take and how long the tiles would need to be laid before the shower can be used. Time is critical for us with my husband being in a wheelchair he can't be without a shower for too long!
im sure you would appreciate that people would need to see the room
but as general rule we would allow between 7 and 10 days to go in and rip out and start from scratch to finish
it can depend on things such as do you use plaster boards and tile direct to them or do you bond and skimm which takes time to dry
are you concreting the floor or use a preformed deck and sit into the floor do you have concrete floor or floor boards and so on and so on
bob
I have just recently finished a wet room, it took me 2 weeks. i shaped the floor with leveling compound to get the fall to the gulley/drain, then i tiled the floor and all the walls. The bathroom was 2.4 meters wide by 5 meters long. In that 2 weeks i also installed the bathroom suite and shower.
Have a look at [b]wetwalling[/b] as this saves on tiling time.
hope this helps
DIY how to tutorial projects and guides - Did you know we have a DIY Projects section? Well, if no, then we certainly do! Within this area of our site have literally hundreds of how-to guides and tutorials that cover a huge range of home improvement tasks. Each page also comes with pictures and a video to make completing those jobs even easier!