Ran out of Concrete Laying Slab for Summer House but What to do now?


Postby symbiosis » Sun Feb 25, 2018 12:40 pm

Hi all
Laid a slab for the foundation of a log cabin summer house last weekend and unfortunately ran out of materials and daylight!!

The result being 1 1/2" under the shuttering and not the smoothest of finishes with some noticeable ripples.

What are my options, can pour another 1 1/2" of concrete on top or am I better off with a thin layer of self levelling compound on top?

Thanks
symbiosis
Rank: Labourer
Progress to next rank:
0%
Posts: 1
Joined: Sun Feb 25, 2018 12:12 pm

Sponsor

Simply Build It

Postby Skid Sprocket » Sun Mar 18, 2018 11:28 pm

! 1/2 ins is a bit thick for self leveling compound and a bit thin for a screed. One option would be to add a 1/2 ins strip of wood on top of the shuttering and then you might get away with a concrete screed (2 ins) of 3 sharp sand to 1 cement.
Skid Sprocket
Rank: Tradesman
Progress to next rank:
65.4%
Posts: 41
Joined: Wed Dec 20, 2017 5:11 pm

Display posts from previous
Sort by
Order by



  • DIY How to Project Guides

  • DIY how to tutorial projects and guides - Did you know we have a DIY Projects section? Well, if no, then we certainly do! Within this area of our site have literally hundreds of how-to guides and tutorials that cover a huge range of home improvement tasks. Each page also comes with pictures and a video to make completing those jobs even easier!



 


  • Related Topics